DEBRIS FLOW PROTECTION

Proje: Borusan EnBW

Place: Erzurum

Country: Türkiye

Year of Installation: 2019

Client: Borusan EnBW

Engineering:  Geobrugg AG

Contractor: Artusa Geohazard Solutions

Initial Situation: At the hydro power plant infrastructure in 2011 and 2017 torrents brought down debris and clogged culverts of the draining system. Around 5'000 m³ of debris damaged the HPP area.
Description: At the ideal place for this debris flow barrier, there also is an area for debris material nearby. The system is a V-shaped, 6 meters high barrier (VX160-H6) with 8 meters deep wire rope anchors.
Installed Sytems: Debris Flow Barrier line VX160-H6
Corrosion Protection: GEOBRUGG SUPERCOATING®
Height: 6.0 m Length: 18.5m Number of Barriers:1

Retention Capacity: 3000 m³

Artusa Services Related to This Project :

- Scaling

- Rock Bolting

- Debris Flow Protection

- Restricted Access Drillings

- Design Services